Latest update on our server's colocation facility power system repairs

Started by Toruk Makto, February 04, 2013, 10:46:56 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

Toruk Makto

For those that noticed the 45 minute downtime last night:

Yep, we took another hit from the faulty power at the colo. (That's four now in 4 months).

 However, there is good news on the power front. The AC and DC cabling for the new Eaton Powerware 9315 225kva UPS at the data enter was completed last Friday and the new unit has been placed. The Eaton tech rep is on site right now configuring and doing final checkouts of the new system. Transfer of the site AC facility is supposed to be transparent, so we should not take a hit from that.

Markì

Lì'fyari leNa'vi 'Rrtamì, vay set 'almong a fra'u zera'u ta ngrrpongu
Na'vi Dictionary: http://files.learnnavi.org/dicts/NaviDictionary.pdf

Toruk Makto

Just heard from the owner of the colocation facility. The new UPS is in place and online now. We shouldn't have any more power hits!

Lì'fyari leNa'vi 'Rrtamì, vay set 'almong a fra'u zera'u ta ngrrpongu
Na'vi Dictionary: http://files.learnnavi.org/dicts/NaviDictionary.pdf

`Eylan Ayfalulukanä

I noticed the downtime last night. I just hope that we weren't responsible for the power outage at the Super Bowl  ;)

Yawey ngahu!
pamrel si ro [email protected]